Antalya Merkez – Manavgat – Serik – Korkuteli İçmesuyu Hatları Yapım İşi

Completed Potable Water Transmission and Networks Antalya 2016
Contracting authority
Antalya Su ve Atıksu İdaresi Genel Müdürlüğü (ASAT)
Type of work
Potable Water Transmission and Networks
Province
Antalya
Status
Completed
Construction period
2016
Contract date
18.08.2016
Completion date
17.10.2017
Contract duration
720 days
Contract value
24,445,000.00 ₺

Record details are taken from the tender contract files. A copy of the authority-approved work completion certificate is supplied on request.

19 photos
08 / Contact

Let us share our qualification file.

If your authority needs a work completion certificate, technical personnel list or plant fleet undertaking for a construction work, fill in the form — our corporate team responds within the same working day.

Head Office — Antalya

Soğuksu Mah. 308 Sok. No:42
Adabel Sit. B Blok 11/38
Muratpaşa / ANTALYA — TÜRKİYE
+90 242 238 40 75

Regional Office — Afyonkarahisar

Güvenevler Mah.
Kocatepe Cad. No:45
Merkez / AFYONKARAHİSAR — TÜRKİYE
+90 272 216 94 53
Bid / document request

Request information on this work: Antalya Merkez – Manavgat – Serik – Korkuteli İçmesuyu Hatları Yapım İşi

Form data is processed solely to respond to your request.